concept · INFO-CS-ADS-186Job Sequencing with Deadlines
Explore how greedy algorithms schedule jobs with deadlines and profits to maximize the total profit when each job requires one unit of time.
Explanation
Overview
Job Sequencing with Deadlines is a scheduling optimization problem in which each job has a deadline and an associated profit. Every job requires one unit of processing time, and a job earns its profit only if it is completed by its deadline. The objective is to choose and arrange jobs to maximize total profit.
Key concepts
Deadline constraints; Profit maximization; Descending profit order; Latest available time slot; Greedy scheduling; Feasibility
Variables
job[i]: An individual job.; deadline[i]: The latest time slot in which job i can be completed.; profit[i]: The profit earned if job i is completed before its deadline.; slot[t]: A time slot assigned to a selected job.; maxDeadline: The largest deadline among the available jobs.
Complexity
sorting: O(n log n) time.; slotSearch: O(nD) time in the straightforward implementation.; overall: O(n log n + nD) time and O(D) auxiliary space.; variables: n is the number of jobs and D is the maximum deadline.
Example
jobs: name: A; deadline: 2; profit: 100; name: B; deadline: 1; profit: 19; scheduledJobs: slot: 1; job: C; slot: 2; job: A; totalProfit: 142; explanation: Jobs are considered in descending order of profit. Each selected job is placed in the latest available slot at or before its deadline, preserving earlier slots for jobs with tighter deadlines.
Pseudocode
function jobSequencing(jobs):
sort jobs by profit in descending order
maxDeadline = maximum deadline among jobs
slots = array of size maxDeadline + 1 filled with empty
totalProfit = 0
for job in jobs:
for t = min(job.deadline, maxDeadline) down to 1:
if slots[t] is empty:
slots[t] = job
totalProfit += job.profit
break
return slots, totalProfit
Applications
Task scheduling.; Production planning.; Deadline-based project selection.; Profit-oriented resource allocation.; Single-machine scheduling.
Variables
Deadline[i]
The latest time slot in which job i can be completed.
Profit[i]
The profit earned if job i is completed before its deadline.
Slot[t]
A time slot assigned to a selected job.
Max Deadline
The largest deadline among the available jobs.
Example or application
Jobs
| Name | Deadline | Profit |
|---|
A | 2 | 100 |
B | 1 | 19 |
C | 2 | 27 |
D | 1 | 25 |
E | 3 | 15 |
Explanation
Jobs are considered in descending order of profit. Each selected job is placed in the latest available slot at or before its deadline, preserving earlier slots for jobs with tighter deadlines.
Definition
Job Sequencing with Deadlines is a scheduling optimization problem in which each job has a deadline and an associated profit. Every job requires one unit of processing time, and a job earns its profit only if it is completed by its deadline. The objective is to choose and arrange jobs to maximize total profit.
Mathematical Representation
Maximize the sum of profit[i] for scheduled jobs, subject to each job being assigned a distinct time slot t satisfying 1 <= t <= deadline[i].
Greedy Strategy
Sort jobs by profit in descending order.
Find the maximum deadline.
Create time slots that are initially empty.
Consider jobs from highest to lowest profit.
For each job, search backward from its deadline for the latest available slot.
Schedule the job if a valid slot exists.
Calculate the total profit of the scheduled jobs.
Pseudocode
function jobSequencing(jobs):
sort jobs by profit in descending order
maxDeadline = maximum deadline among jobs
slots = array of size maxDeadline + 1 filled with empty
totalProfit = 0
for job in jobs:
for t = min(job.deadline, maxDeadline) down to 1:
if slots[t] is empty:
slots[t] = job
totalProfit += job.profit
break
return slots, totalProfit
Complexity
Slot Search
O(nD) time in the straightforward implementation.
Overall
O(n log n + nD) time and O(D) auxiliary space.
Variables
n is the number of jobs and D is the maximum deadline.
Advantages
Produces an optimal schedule under the standard unit-time job assumptions.
Prioritizes jobs that provide higher profit.
Uses a relatively simple greedy strategy.
Can be optimized using disjoint-set data structures for finding available slots.
Limitations
The standard method assumes every job takes exactly one unit of time.
Jobs with different processing times require a different scheduling model.
The algorithm must respect deadline feasibility when assigning slots.
Additional constraints such as job dependencies may invalidate the simple greedy strategy.
Applications
Task scheduling.
Production planning.
Deadline-based project selection.
Profit-oriented resource allocation.
Single-machine scheduling.
Practice Question
Why does the algorithm place a selected job in the latest available slot before its deadline?
Practice Answer
It preserves earlier time slots for other jobs with tighter deadlines.
Learning Objectives
Explain the central idea and purpose of job sequencing with deadlines.
Identify the assumptions, inputs, and conditions relevant to job sequencing with deadlines.
Evaluate an application of job sequencing with deadlines for correctness and practical resource requirements.
Sources and verification
Sources are shown as provided in the project data. Not every source has yet been independently verified. Please report errors or missing citations.
- Greedy Algorithms and Optimization
Suggest a correction or source · More in Algorithms & Data Structures